Menaiktaraf Jalan Ayer Keroh Ke Bandar Melaka [Fasa 1: Pembinaaan Persimpangan Peringgit Dan Persimpangan MITC Interchange No.7]
Carried out alternative Design of the bridge using cast in-situ Segmental Box Girder by Balanced Cantilever Construction method.
Designed the monolith cantilever crosshead to support the 120m main spans box girder bridge to avoid numerous traffic obstruction during construction over a busy traffic junction.
Reviewed and approved the contractor’s proposal and submissions of the temporary work and construction methods.